flexiblefullpage - default
interstitial1 - interstitial
Currently Reading

Work in Progress

Advertisement
billboard -
Design

Work in Progress

A look behind the walls of the New American Remodel 


By By Charlie Wardell January 15, 2019
This article first appeared in the January 2019 issue of Pro Remodeler.

When asked what the most difficult part of this year’s New American Remodel has been, Michael Gardner pauses for a moment then laughs. “All of it,” he says. “It’s been an evolving project with lots of design tweaks, changes, and resolutions as we worked our way through.”

Of course, adaptability is a must for anyone in this business, but this project tested the Las Vegas architect/remodeler’s management skills and determination. The fact that it’s coming together so well and will be ready by the deadline is a testament to Gardner and his team.

Not the Smoothest Start

Complications started soon after work began. The first order of business was the removal of some asbestos siding, but the schedule had accounted for that. What no one anticipated was that the existing home’s exterior walls would prove useless for structural purposes. The shortcoming announced itself with some drama: Not long after crews removed the siding and roof from the 1950s ranch, a strong wind blew through town and knocked over half the existing CMU exterior walls. 

That was a surprise: Pre-demolition magnetic scans had detected metal in the walls, which everyone assumed, wrongly, was rebar. It was just metal conduit with no structural value. Without the bracing provided by the roof, the walls had no lateral strength. 

Although losing the walls didn’t necessitate any design changes, Gardner did have to tweak the wall locations a bit and take a different approach to supporting the second floor and roof. His Plan B was to carry those loads with new, wood-framed walls placed next to the old CMUs. 

To get bearing for the framed walls, workers cut away parts of the old slab. They then poured new reinforced footings—a step that also hadn’t been figured into the original schedule.

Design glitches after that were mostly minor. The trusses, for instance, arrived with the webs laid out backwards, which threw off the spacing and forced Gardner to use flexible HVAC duct instead of rigid duct. It was less than optimal from an airflow perspective, but the schedule didn’t leave time for new trusses.

As the project moved along, the two most significant, ongoing issues had to do with labor availability and materials delivery.

Remaining Challenges

Labor shortages certainly aren’t unique to this home, but while skilled trades are scarce everywhere, they’re especially scarce in Vegas. Gardner addressed the problem in three ways: by using small trade contractors eager for the chance to work on a high-profile project; by looking for companies that could do the work of two or more trades; and by obsessively managing the schedule to ensure that the job was ready for each trade when they arrived.

A Successful Project

The bottom line is this project had more changes than most, which only made scheduling more difficult.

At this writing, the home is on track to be ready for tours during the International Builders’ Show from Feb 19-21, thanks to weeks of 12-hour days with no time off. We will feature the finished home next month. 

Meanwhile, here are some photos to help you understand what it has taken to get there.

—Rough Framing—

The old walls were 7 feet 10 inches high—low for a contemporary home—so the remodel would include raising the ceiling heights. Gardner wanted a thick roof system that would accommodate mechanicals but didn’t want the edge of the home to look too heavy. The use of a tapered fascia allowed for both and also supported the goal of a facade that didn’t look like the typical modern home. The design called for wide openings between the outdoor room and the pool, with screens that retracted overhead.

—Interior Framing Details—

While wood did the job for the first-floor headers, steel was a better solution for the large second-floor openings. A new type of light-gauge moment frame helps stiffen the structure against the high winds that the area sometimes experiences.

Complex structures like this often use steel I-beams as headers for large openings. However, it was clear from the beginning that meeting the project schedule would require more adaptability than would be possible with steel. Thick wood beams take less time to get and can be modified in the field, which is why they were chosen for the first-floor openings.

 

The elevator posed a challenge: Placing it inside the existing home’s footprint would mean cutting the slab to accommodate it. Locating it outside the slab proved an easier solution.

Although the exterior walls were insulated with spray foam, a foil-backed paper product with internal air pockets raised the R-value and let them reduce foam thickness.

—Waterproofing—

Gardner hired a local concrete coating company to waterproof the upper balcony deck. Their system combines specially formulated acrylic resins with multidirectional chopped fiberglass mat for a tough yet flexible coating. It was finished with tile backer and porcelain tile. 

The home uses a commercial roof system that consists of a membrane placed over 4½-inch closed-cell foam. Not only did this eliminate thermal bridging, but running ductwork and wiring through an uninsulated ceiling cavity meant that any changes needed later on would be a lot easier. 

 

—Exterior Finishes—

The entire house was wrapped with a drainable water-resistive barrier, which also serves as an air barrier. The siding is a mix of metal, manufactured stone veneer and Brazilian teak shiplap. “Much of Vegas is about stone and stucco, but we wanted to include metal and wood in the mix to create a more organic feel,” says Gardner. 

 


written by

Charlie Wardell

Charlie Wardell is a freelance writer and former remodeler in Tisbury, Mass.


Add new comment

Plain text

  • No HTML tags allowed.
  • Web page addresses and email addresses turn into links automatically.
  • Lines and paragraphs break automatically.
leaderboard2 - default

Related Stories

Designing, Building, and Installing a Luxury Custom Wine Cube

An 11-foot wine cube enveloping a pantry is the stand out feature of this customized New York penthouse

Marvin Releases Switchable Privacy Glass Window

The privacy glass windows can be purchased from Marvin's Direct Glaze windows

Building A Small Projects Division from the Ground Up

Through hard work and careful strategy, Harth Home Services has seen big growth

Client Design Choices in the Time of Social Media and AI

Social media speeds up the trend cycles, and now artificially created images are falling into homeowners' hands

Design Trends to Watch in 2024

What’s in and out for the upcoming year? Remodeling designers share insights

Benjamin Moore Announces its Color of the Year 2024

Will next year be the year of blues?

Color of the Year 2024 Announced by Sherwin-Williams

The color is set to mimic ever-present peace

Insights for Designing Outdoor Kitchens

Was the pandemic-fueled thirst for outdoor kitchen remodels and additions a fluke, or is it here to stay? Plus: The top design considerations for outdoor kitchens

Home Run Remodeling Lessons: The New American Remodel 2023

A final look at The New American Remodel 2023

Webinar: From Disjointed Design to Cohesive and Efficient—The New American Remodel 2023

Access the recording for the first The New American Remodel webinar held on March 8 at 2 pm CT

Advertisement
boombox2 -
Advertisement
halfpage2 -
Advertisement
native1 -

More in Category




Advertisement
native2 -
Advertisement
halfpage1 -
Advertisement
leaderboard1 -